Profile summary:
Prepare Procurement Material approval plan list based on the Contractual Documents (BOQ). Identify the suitable 9COM ref no for the materials in the PMAP list. Follow Saudi Aramco Material Specialist to get the 9COM/ 9CAT screenshot that contains the approved Manufacturer/ Approved Vendor details. Identify the Level of Inspection of the listed materials from the 9COM screenshot as well as the Saudi Aramco Engineering Procedure SAEP 1151.Based on the inspection levels (Non-Inspectable, Level 0, Level 1, Level 2, Level 3 & Level 4), the approval documents such as Material Technical Approval (MTA for Non-Inspectable materials), Material Requisition Package (MR for Level 0 to Level 4 inspectable materials), Order Placement Recommendation (OPR for Inspectable Materials), Inspection Assignment Package (IAP for Level 1 to Level 4 Inspectable Materials).Inspection level waiver will be applied as per Saudi Aramco Engineer Procedure SAEP 347..